3号機の事象進展

以下、NEA/CSNI“Benchmark Study of the Accident at the Fukushima Daiichi Nuclear Power Plant (BSAF Project) Phase I Summary Report”(2015), p.17.より引用

No Date Time[s] Time[h] Event
1 3/11 14:46:00 0 0.00 Earthquake
2 3/11 14:47:35 95 0.03 Reactor scram
3 3/11 14:48:45 165 0.05 MSIV closed
4 3/11 15:05:00 1,140 0.32 RCIC manually started
5 3/11 15:25:00 2,340 0.65 RCIC automatically tripped (L-8)
6 3/11 15:36:00 3,000 0.83 Tsunami hit
7 3/11 15:38:00 3,120 0.87 Station black-out
8 3/11 16:03:00 4,620 1.28 RCIC manually started
9 3/12 11:36:00 75,000 20.83 RCIC automatically tripped
10 3/12 12:06:00 76,800 21.33 Alternative S/C spray by DDFP
11 3/12 12:35:00 78,540 21.82 HPCI automatically started (L-2)
12 3/13 02:42:00 129,360 35.93 HPCI manually stopped
13 3/13 03:05:00 130,740 36.32 Alternative S/C spray by DDFP was stopped. Completion of switchover to alternative water injection into the reactor reported to MCR
14 3/13 05:08:00 138,120 38.37 Alternative S/C spray by DDFP started (switched over from the alternative water injection line into the reactor)
15 3/13 07:39:00 147,180 40.88 Alternative D/W spray by DDFP started (switched over from the alternative S/C spray)
16 3/13 07:43:00 147,420 40.95 Alternative S/C spray by DDFP was halted
17 3/13 08:40:00 to 09:10:00 150,840 to 152,640 41.9 to 42.4 Alternative D/W spray by DDFP halted. Switched over to alternative water injection line into the reactor.
18 around 3/13 09:08:00 around 152,520 around 42.37 Reactor depressurized
19 3/13 09:20:00 153,240 42.57 PCV pressure decrease by venting confirmed
20 3/13 09:25:00 153,540 42.65 Freshwater injection started by fire engines
21 3/13 11:17:00 160,260 44.52 Closure of AO-valve of S/C venting line confirmed due to loss of driving gas pressure
22 3/13 12:20:00 164,040 45.57 Freshwater injection terminated due to water inventory depletion in fire protection pools. Switching over to seawater injection started
23 3/13 12:30:00 164,640 45.73 S/C vent valve opened for PCV venting
24 3/13 13:12:00 167,160 46.43 Seawater injection line configured and injection started
25 3/14 01:10:00 210,240 58.40 Water injection halted to make up the water source pit
26 3/14 03:20:00 218,040 60.57 Water source pit make up done. Seawater injection resumed
27 3/14 05:20:00 225,240 62.57 Small S/C vent valve (AO) opening started for PCV venting
28 3/14 06:10:00 228,240 63.40 Small S/C vent valve (AO) opening started for PCV venting
29 3/14 11:01:00 245,700 68.25 Unit 3 reactor building exploded
30 3/14 11:01:00 245,700 68.25 Seawater injection halted (as consequence of the explosion)
31 3/14 15:30:00 261,840 72.73 Seawater injection resumed
32 3/14 19:30:00 to 19:54:00 276,240 to 277,680 76.73 to 77.13 Seawater injection halted (fire engines found to have been out-of-service from 30 min to 1 hour before 19:20)
33 3/14 21:14:00 282,480 78.47 Seawater injection halted
34 3/15 02:30:00 301,440 83.73 Seawater injection resumed
35 3/15 16:05:00 350,340 97.32 S/C vent valve closure assumed for PCV venting