| 1 | 3/11 14:46:00 | 0 | 0.00 | Earthquake | 
      
         | 2 | 3/11 14:47:32 | 92 | 0.03 | Reactor scram | 
      
         | 3 | 3/11 14:48:29 | 149 | 0.03 | MSIV closed | 
      
         | 4 | 3/11 14:52:00 | 360 | 0.10 | IC (A) (B) automatic start-up | 
      
         | 5 | 3/11 15:03:00 | 1,020 | 0.28 | IC (A) (B) stopped | 
      
         | 6 | 3/11 15:05:00 | 1,140 | 0.32 | CCS torus cooling (A) in service | 
      
         | 7 | 3/11 15:10:00 | 1,440 | 0.40 | CCS torus cooling (B) in service | 
      
         | 8 | 3/11 15:17:00 | 1,860 | 0.52 | IC (A) restarted | 
      
         | 9 | 3/11 15:19:00 | 1,980 | 0.55 | IC (A) stopped | 
      
         | 10 | 3/11 15:24:00 | 2,280 | 0.63 | IC (A) restarted | 
      
         | 11 | 3/11 15:26:00 | 2,400 | 0.67 | IC (A) stopped | 
      
         | 12 | 3/11 15:32:00 | 2,760 | 0.77 | IC (A) restarted | 
      
         | 13 | 3/11 15:34:00 | 2,880 | 0.80 | IC (A) stopped | 
      
         | 14 | 3/11 15:36:00 | 3,000 | 0.83 | Tsunami hit | 
      
         | 15 | 3/11 15:37:00 | 3,060 | 0.85 | Station blackout | 
      
         | 16 | 3/11 18:18:00 | 12,720 | 3.53 | IC (A) valves 2A, 3A opened (steam generation confirmed) | 
      
         | 17 | 3/11 18:25:00 | 13,140 | 3.65 | IC (A) valve 3A closed | 
      
         | 18 | 3/11 20:50:00 | 21,840 | 6.07 | Alternative water injection lines composed of DDFP started up (stand-by for injection after reactor depressurization) | 
      
         | 19 | 3/11 21:00:00 | 22,440 | 6.23 | Operators who entered the reactor building had their APD showing 0.8 mSv | 
      
         | 20 | 3/11 21:30:00 | 24,240 | 6.73 | IC (A) valve 3A opened (steam generation confirmed) | 
      
         | 21 | 3/12 01:48:00 | 39,720 | 11.03 | DDFP stopped | 
      
         | 22 | 3/12 04:00:00 | 47,640 | 13.23 | Freshwater injected | 
      
         | 23 | 3/12 04:02:00 | 47,760 | 13.27 | Fresh water injection by fire engines completed | 
      
         | 24 | 3/12 05:46:00 | 54,000 | 15.00 | Freshwater injection by fire engines resumed | 
      
         | 25 | 3/12 10:40:00 | 71,650 | 19.90 | High dose rate measured at the main gate after attempts to open the small S/C vent valve | 
      
         | 26 | 3/12 14:30:00 | 85,440 | 23.73 | PCV pressure decrease confirmed upon AO valve operation on S/C side for PCV venting at 10:17 | 
      
         | 27 | 3/12 14:53:00 | 86,820 | 24.12 | Freshwater injection completed | 
      
         | 28 | 3/12 15:27:00 | 88,860 | 24.68 | PCV venting valve closed | 
      
         | 29 | 3/12 15:36:00 | 89,400 | 24.83 | Unit-1 reactor building exploded | 
      
         | 30 | 3/12 19:04:00 | 101,880 | 28.30 | Seawater injection started by fire engines | 
      
         | 31 | 3/12 21:45:00 | 111,540 | 30.98 | Seawater injection stopped | 
      
         | 32 | 3/12 23:50:00 | 119,040 | 33.07 | Seawater injection resumed | 
      
         | 33 | 3/14 01:10:00 | 210,240 | 58.40 | Seawater injection stopped | 
      
         | 34 | 3/14 20:00:00 | 278,040 | 77.23 | Seawater injection resumed |