Fuel removal from the spent fuel pool

Work to extract the fuel from the spent fuel pools is proceeding steadily

Status of Progress Points

Preparations to begin extracting the fuel from within the Unit 4 spent fuel pool (to start by December 2013), which is the primary objective for Term 1, are proceeding steadily.

(1) Pool circulation cooling, desalination, and ascertaining conditions within the pool such as corrosion, etc.

  • Cooling equipment was restored and the pools are being cooled in a stable manner (Unit 1: August 10, 2011 ~, Unit 2: May 31, 2011 ~, Unit 3: June 30, 2011 ~, Unit 4: July 31, 2011 ~).
  • Pool water is being desalinated (Unit 2, 4 completed. Unit 3 being desalinated.)
  • Conditions within the pool had been ascertained using remote-control cameras and the state of corrosion due to the extraction of new fuel has been confirmed.

(2) Removal of debris from the top of the building and construction of a cover in preparation for fuel removal

  • Debris on top of the reactor buildings is being removed (Unit 3: Debris being removed, Unit 4: Debris being gathered).
  • A fuel removal cover for Unit 4* continues to be built. Construction should be completed to enable fuel removal start a month earlier in December 2013.

(3) Common pool repair, Temporary cask custody area construction, etc.

  • Repairs on the common pool in order to store extracted spent fuel and construction of Temporary cask custody area facilities is ongoing.
※the fuel removal cover shall be a structure built to support fuel handling equipment, provide a suitable work environment and prevent the dispersion and proliferation of radioactive materials.

 

Removal of debris from top of Unit 3, Unit 4 reactor buildings and construction of Unit 4 cover for fuel removal

  • Debris is currently being removed from the top of the Unit 3 reactor building in preparation for fuel removal from the spent fuel pool ( to be completed around the end of FY2012)
  • Unstable pieces of steel girder fell into the fuel pool during debris removal at Unit 3. A report on the cause of this incident and reoccurrence prevention countermeasures was submitted to the Nuclear Regulatory Commission (10/3,19 and 11/15). Debris removal work will continue safely and steadily based on this report.
  • At Unit 4 building debris was removed on July 11 and large equipment was removed between July 24 and October 2. debris is currently being gathered (until December). In conjunction, a fuel removal cover continues to be built (to be finished around the middle of FY2013)

 

Inspecting the soundness of fresh fuel (unirradiated fuel) inside the Unit 4 SFP

  • In order to inspect the status of fuel corrosion to fresh fuel assemblies were removed from the pool and soundness was evaluated (August 27 through the 29th)
  • The inspection revealed no significant information or damage to the fuel rods were fuel structures, and no corrosion was found, and it was therefore concluded that material corrosion will not have a large impact on fuel removal.

 

Unit 3, Unit 4 SFP debris dispersion survey

  • Underwater cameras and remotely operated vehicles (ROV) were used to survey the dispersion of debris within the spent fuel pools.
  • An underwater debris removal plan prior to spent fuel removal shall be proposed based on the results of the survey.

 

Unit 1, Unit 2 operating floor survey

  • A survey of the operating floors was conducted in order to help with the deliberation of fuel removal from spent fuel pools.
  • At Unit 1 a camera attached to a balloon was used to take footage and to measure dose levels. A maximum dose of 53.6mSv/h was measured at a 1 m from the operating floor.
  • At Unit 2 a remote-controlled robot was used to take footage, and measure radiation levels and temperature/humidity levels. A maximum dose of 880mSv/h was measured at the top of the reactor well.

 

Desalination of Unit 1~4 spent fuel pools

  • Unit 1: Saline levels are low enough since seawater was not injected
  • Unit 2: Desalination completed on July 2. Water quality being monitored through periodic sampling.
  • Unit 3: Being desalinated with desalination equipment
  • Unit 4: Desalination completed on October 12. Water quality being monitored through periodic sampling
  • Close range chloride ion concentration: Unit 1 5ppm(7/17), Unit 2 28ppm(10/18)Unit 2 72ppm(10/18), Unit 49ppm(10/18)(Below technical specification limits of 100ppm)

Future issues and the direction of countermeasures

Handling the risks associated with earthquakes and tsunami

  • Alternative coolant injection equipment, such as concrete pump trucks, having been deployed so as to enable sufficient time to restore cooling function if the fuel pools become unable to be cooled due to damage to primary/secondary pump pipes, etc., by an earthquake or tsunami.
    • In this instance, it has been concluded that a minimum of 16 days (Unit 4 ) would be required to reach a point where fuel pool water level is maintained at a certain level (2m from top of active fuel: water level at which shielding is deemed effective) since water temperatures will rise and water levels will decrease.
    • Even if it is difficult to cool the pools using emergency coolant injection equipment, and concrete pump trucks, etc., are used to cool the pools, cooling could be restored in approximately 6 hours even if cooling function is lost
  • Furthermore, every effort shall be made to comply with newly gained knowledge, including the handling of changes to the reference ground motion.

 

Issues that may impact work schedules

  • The following issues that may impact work schedules must be resolved in order to carry out fuel removal as planned.
    • Debris removal work: the status of falling debris within the pools and radiation levels have yet to be confirmed which may prolong work and add to it.
    • Fuel removal cover construction: many uncertainties, such as building damage and radiation levels, exist that may prolong or add to work.
    • Pool fuel removal work: if more of the fuel than expected is damaged, or if the extent of damage to the fuel is greater than expected, work may be prolonged or added to.

Unit 1, Unit 2 fuel removal

  • Detailed plans shall be proposed based on a survey of debris at Unit 1 while acquiring knowledge and experience through removing debris at Unit 3 and Unit 4, the operability and malfunctions of remote operated equipment and fuel surveys, etc.
  • Detailed plans for the inspection, repair, and fuel removal at Unit 2 shall be proposed based on the establishment of remote decontamination technology and upon decontaminating the inside of the building, shielding it and conducting surveys at a point in time when fuel handling equipment can be approached.


UnitDescriptionCategoryDate of issueLink
Unit 4 Work Procedure Review Following Unused Fuel Removal at Fukushima Daiichi NPS Unit 4 Document 25 November 2013
  • PDF
Unit 4 Current Status of Fukushima Daiichi NPS Unit 4 Fuel Removal Document & photos 18 November 2013
  • PDF
Unit 4 Operation of Fuel Removal from Unit 4 Spent Fuel Pool at Fukushima Daiichi NPS Document & photos 15 November 2013
  • PDF
Unit 4 Summary of results of external and internal reviews made on the operation to remove fuel at Fukushima Daiichi NPS Unit 4 Document 15 November 2013
  • PDF
Unit 4 Safety Measures etc. concerning Fuel Removal from Unit 4 in Fukushima Daiichi NPS Document 15 November 2013
  • PDF
Unit 4 Operation to Remove Spent Fuel from Unit 4 Spent Fuel Pool at Fukushima Daiichi NPS Document & photos 13 November 2013
  • PDF
Unit 4 Results of Inside Investigation of the Reactor Well, the RPV and the Spent Fuel Pool at Unit 4 in Fukushima Daiichi Nuclear Power Station Document & photos 09 August 2013
  • PDF
Unit 4 Inside Investigation of the Reactor Well, the RPV and the Spent Fuel Pool of Unit 4 at Fukushima Daiichi Nuclear Power Station Document 02 August 2013
  • PDF
Unit 4 Completion of Outer Wall and Exterior Roof Panel Installation for the Fuel Removal Cover at Unit 4 in Fukushima Daiichi Nuclear Power Station Document & photos 22 July 2013
  • PDF
Unit 4 Completion of the Steel Frame Construction for the Cover to be Installed for Fuel Removal at Unit 4 at Fukushima Daiichi Nuclear Power Station Document & photos 29 May 2013
  • PDF
Unit 3 Debris Removal from the Upper Part of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station Renewal of the Protection Installed on the Spent Fuel Pool and the Skimmer Surge Tank Hatch Document & photos 27 May 2013
  • PDF
Unit 3 Debris Removal from the Upper Part of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station Document & photos 22 April 2013
  • PDF
Unit 4 Progress of the Steel Frame Construction for the Cover to be Installed for Fuel Removal at Unit 4 at Fukushima Daiichi Nuclear Power Station Document & photos 11 April 2013
  • PDF
n/a Transportation of a Dry Storage Cask from the Common Pool Building to the Temporary Dry Cask Storage Facility in Fukushima Daiichi Nuclear Power Station Document & photos 04 April 2013
  • PDF
Unit 3 Desalting Completed at Unit 3 Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station Document & photos 18 March 2013
  • PDF
Unit 4 Steel Frame Construction for the Cover to be Installed for Fuel Removal at Unit 4 at Fukushima Daiichi Nuclear Power Station: Completion of the Third Layer of Steel Frame Document & photos 13 March 2013
  • PDF
Units 1-4 Cask Transportation to Fukushima Daiichi Nuclear Power Station by Way of the Port of Hirono Thermal Power Station Document & photos 28 February 2013
  • PDF
Unit 3 Investigation of the Inside of Spent Fuel Pool Utilizing an Underwater Camera as Part of Debris Removal from the Upper Part of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station Document & photos 13 February 2013
  • PDF
Unit 3 Possibility of Debris (Assumed to be the Fuel Handling Machine Mast) Sinking in the Spent Fuel Pool at Debris Removal from the Upper Part of the Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station(2) Document & photos 08 February 2013
  • PDF
Unit 3 Possibility of Debris (Assumed to be the Fuel Handling Machine Mast) Sinking in the Spent Fuel Pool at Debris Removal from the Upper Part of the Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station Document & photos 08 February 2013
  • PDF
Unit 3 Debris Removal from the Upper part of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station: Removal of Steel Truss Debris Document & photos 06 February 2013
  • PDF
Unit 3 Debris Removal from the Upper Part of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station Document & photos 04 February 2013
  • PDF
Unit 4 Steel Framing Construction for the Cover to be Installed for Fuel Removal at Unit 4 at Fukushima Daiichi Nuclear Power Station: Installation of 2 Columns of the First Layer Document & photos 08 January 2013
  • PDF
Unit 4 Steel Beam Framing for the Cover to be Installed for Fuel Removal at Unit 4 at Fukushima Daiichi Nuclear Power Station Document 07 January 2013
  • PDF
n/a Inspection of the Spent Fuel Appearance and the Fuel Rack in the Spent Fuel Common Pool at Fukushima Daiichi Nuclear Power Station Document 20 December 2012
  • PDF
Unit 1 Results of Reinvestigation of Unit 1 Operation Floor at Fukushima Daiichi Nuclear Power Station Document 24 October 2012
  • PDF
Unit 3 Presumption of Refueling machine’s situation based on the result Unit 3 Spent Fuel Pool investigation Document & photos 15 October 2012
  • PDF
Unit 3 Investigation of the Inside of Unit 3 Spent Fuel Pool using an Underwater Camera at Fukushima Daiichi NPP Document & photos 15 October 2012
  • PDF
Unit 4 Desalting Completed at Unit 4 Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station Document & photos 12 October 2012
  • PDF
Unit 3 Investigation of the Inside of Unit 3 Spent Fuel Pool Using an Underwater Camera at Fukushima Daiichi Nuclear Power Station (September 26) Document & photos 26 September 2012
  • PDF
Unit 3 Investigation of the Inside of Unit 3 Spent Fuel Pool Using an Underwater Camera at Fukushima Daiichi Nuclear Power Station Document & photos 25 September 2012
  • PDF
Unit 3 Investigation of the Inside of the Spent Fuel Pool for Fuel Removal from the Upper Part of Unit 3 Reactor Building at Fukushima Daiichi Nuclear Power Station Document & photos 13 September 2012
  • PDF
Unit 4 The Soundness of Unit 4 Reactor Building and Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station Document & photos 30 August 2012
  • PDF
Unit 4 Results of the Second Soundness Inspection of Unit 4 Reactor Building at Fukushima Daiichi Nuclear Power Station Document & photos 30 August 2012
  • PDF
Unit 4 Soundness Investigation of the Unused (Unirradiated) Fuel Removed from Unit 4 Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station Document & photos 29 August 2012
  • PDF
Unit 4 Soundness Investigation of the Unused (Unirradiated) Fuel Removed from Unit 4 Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station Document & photos 28 August 2012
  • PDF
Unit 4 Unused Fuel Removal from Unit 4 Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station photos 19 July 2012
  • PDF
Unit 4 Completion of Debris Removal from the Upper Part of Unit 4 Reactor Building at Fukushima Daiichi Nuclear Power Station Document & photos 11 July 2012
  • PDF
Unit 4 Unit 4 Spent Fuel Pool Circulation Cooling System UPS Inside Inspection Document & photos 06 July 2012
  • PDF
Unit 2 Unit 2 Spent Fuel Pool Desalination Completed at Fukushima Daiichi Nuclear Power Station Document & photos 02 July 2012
  • PDF
Unit 4 Unit 4 Spent Fuel Pool Alternative Cooling System Suspended at Fukushima Daiichi Nuclear Power Station(Occurred on June 30, 2012) Document 02 July 2012
  • PDF
Unit 4 The Protection Platform Installation on Unit 4 Spent Fuel Pool at Fukushima Daiichi Power Station Document & photos 15 June 2012
  • PDF
Unit 4 The Protection Platform Added on Unit 4 Spent Fuel Pool at Fukushima Daiichi Power Station Document & photos 08 June 2012
  • PDF
Unit 4 Motor Cable Connection for the Secondary System Circulation Pump (B) of Unit 4 Spent Fuel Pool Circulation Cooling System at Fukushima Daiichi Nuclear Power Station photos 08 June 2012
  • PDF
Unit 4 The integrity evaluation of the reactor building at unit4 in the Fukushima Daiichi nuclear power station Document & photos 16 May 2012
  • PDF
Unit 4 Soundness Verification of Unit 4 Reactor Building at Fukushima Daiichi Nuclear Power Station Document 16 May 2012
  • PDF
Unit 4 Set up of Manned Heavy Machinery on the upper side of Unit 4 Reactor Building In the Fukushima Daiichi Nuclear Power Station Document & photos 16 April 2012
  • PDF
Unit 4 Fukushima Daiichi Nuclear Power Station, Unit 4 Water Level Measurement for the Verification of Reactor Building Health Document 13 April 2012
  • PDF
Unit 3 Survey on the inside of Unit 3 Spent Fuel Pool for Removal of Debris ,Fukushima Daiichi Nuclear Power Station Document & photos 13 April 2012
  • PDF
Unit 4 Removal Works of Debris on the Upper Part of the Reactor Building of Unit 4 in Fukushima Daiichi Nuclear Power Station photos 06 March 2012
  • PDF
Unit 3 Completion of Removal of Radioactive Materials from Unit 3 Spent Fuel Pool at Fukushima Daiichi Nuclear Power Station Document 02 March 2012
  • PDF
Unit 1 & 2 & 3 & 4 & 5 Response training to abnormal conditions that occurred at Spent Fuel Pool per the Safety Regulation photos 26 January 2012
  • PDF
Unit 2 & 3 & 4 Completion of radioactive materials removal procedure in the spent fuel pool of Unit 2 at Fukushima Daiichi Nuclear Power Station Document 06 December 2011
  • PDF
Unit4 Resumption of desalting by ion exchanging device at spent fuel pool of Unit4 at Fukushima Daiichi Nuclear Power Plant Document & photos 29 November 2011
  • PDF
Unit 3 Strainer washing due to Suction pressure decrease of Primary coolant system pump, in Spent fuel pool closed loop cooling system at Fukushima Daiichi Nuclear Power Station Unit 3 Document 07 November 2011
  • PDF
Unit 2 Installation Status of Radioactive Material Removal Facility at the Unit 2’s Spent Fuel Pool of Fukushima Daiichi Nuclear Power Station photos 07 November 2011
  • PDF
Unit 2 Installation of Radioactive Material Removal Instruments for the Spent Fuel Pool of Unit 2, Fukushima Daiichi Nuclear Power Station Document 06 November 2011
  • PDF
Unit4 Coverage of Spent Fuel Pool for removal of debris on the roof of Reactor Building at Unit 4, Fukushima Daiichi Nuclear Power Station (image) Document & photos 27 September 2011
  • PDF
Unit4 Unit 4, Fukushima Daiichi NPS circulating cooling system for Spent Fuel Pool Water seepage from a flexible hose Document 08 September 2011
  • PDF
Unit4 Unit 4 Spent Fuel Pool Circulating Cooling System Oozing Water from Flexible Hose Document 23 August 2011
  • PDF
Unit4 Desalting Facilities for Spent Fuel Pool at Unit 4, Fukushima Daiichi Nuclear Power Station photos 20 August 2011
  • PDF
Unit4 Installation of a Salt Removal System at Spent Fuel Pool of Unit 4, Fukushima Daiichi Nuclear Power Station Document 16 August 2011
  • PDF
Unit4 Completion of Installation of Supporting Structure under the Bottom of the Spent Fuel Pool in the Reactor Building at Fukushima Daiichi Nuclear Power Station Unit 4 Document & photos 30 July 2011
  • PDF
Unit4 Spent Fuel Pool in Reactor Building (5th floor), Unit 4, Fukushima Daiichi Nuclear Power Station photos 01 July 2011
  • PDF
Unit4 R/B, Unit 4, Fukushima Daiichi Nuclear Power Station Installation work of supporting structure at the bottom of Spent Fuel Pool (Completion of installation of steel support pillars) Document & photos 20 June 2011
  • PDF
Unit 1 Water injection to reactor well and drier separator pool of Unit 1 in 1F Document 20 June 2011
  • PDF
Unit4 Alternative water injection line to Unit 4 spent fuel pool Document 16 June 2011
  • PDF
Unit 1 & 2 & 3 & 4 Partially correction of amount injected water to spent fuel pool at Fukushima Daiichi Nuclear Power Station Document 01 May 2011
  • PDF