Summary of Decommissioning and Contaminated Water Management
Main works and steps for decommissioning
Fuel removal from Unit 4 SFP had been completed and preparatory works to remove fuel from Unit 1-3 SFP and fuel debris (Note 1) removal are ongoing.
Toward fuel removal from pool
Installation of a cover for fuel removal at Unit 3
Installation of the west-side stopper (February 7, 2017)
- Toward fuel removal from Unit 3 SFP, works to install the cover are underway.
- As measures to reduce the dose on the Reactor Building operating floor, decontamination and installation of shields were completed in June and December 2016 respectively.
- Installation of a cover for fuel removal started from January 2017.
Three principles behind contaminated water countermeasures
Countermeasures for contaminated water are implemented in accordance with the following three principles:
1. Eliminate contamination sources
- â‘ Multi-nuclide removal equipment, etc.
- â‘¡ Remove contaminated water in the trench (Note 3)
2. Isolate water from contamination
- â‘¢ Pump up ground water for bypassing
- â‘£ Pump up ground water near buildings
- ⑤ Land-side impermeable walls
- â‘¥ Waterproof pavement
3. Prevent leakage of contaminated water
- ⑦ Soil improvement by sodium silicate
- ⑧ Sea-side impermeable walls
- ⑨ Increase tanks (welded-joint tanks)
(Note 3) Underground tunnel containing pipes.
Multi-nuclide removal equipment (ALPS), etc.
High-performance multi-nuclide removal equipment
- This equipment removes radionuclides from the contaminated water in tanks and reduces risks.
- Treatment of contaminated water (RO concentrated salt water) was completed in May 2015 via multi-nuclide removal equipment, additional multi-nuclide removal equipment installed by TEPCO (operation commenced in September 2014) and a subsidy project of the Japanese Government (operation commenced in October 2014).
- Strontium-treated water from equipment other than ALPS is being re-treated in ALPS.
Land-side impermeable walls
Opening/closure of frozen pipes
- Land-side impermeable walls surround the buildings and reduce groundwater inflow into the same.
- Freezing started on the sea side and part of the mountain side from March 2016 and on 95% of the mountain side from June 2016. From December 2016, freezing started for two of seven unfrozen sections on the mountain side.
- On the sea side, the underground temperature declined below 0℃ throughout the scope requiring freezing except the unfrozen parts under the seawater pipe trenches and the areas above groundwater level in October 2016.
Sea-side impermeable walls
Sea-side impermeable walls
- Impermeable walls are being installed on the sea side of Units 1-4, to prevent the contaminated groundwater from flowing into the sea.
- The installation of steel pipe sheet piles was completed in September 2015 and they were connected in October 2015. These works completed the closure of sea-side impermeable walls.